Prospect House - 1962 (Prospect Mountain)

1962 Built – $1,254,000
Architect: Shepley Bulfinch Richardson & Abbott
1962-63 Prospect landscaping – $50,000
Architect: Olmsted Associates
1965 Partition soundproofing
1968 Berkshire/Prospect boiler – $8,600
Engineer: Richard J. Libardi
1972 New doorways
1974 Wall soundproofing
1979 Fitch/Prospect steam line – $16,000
1979 Stairwell carpeting – $14,500
1980 Acoustical survey – $2,000
1984 Carpet rooms – $41,740
1985 Roof – $15,000
1985-86 Replace mattresses – $4,686
1986 Window replacement – $13,550
1986 Patio – $47,950
1986 Sound – $5,000
1990-91 Acoustics – $64,797
1998-99 Prospect/Fitch metal railing – $5,200
2004 Phase I – Summer ’04 Renovation Project – renovate 1/2 of Prospect and relocate Radio Station to basement
Phase I Design – $250,000
Student Life Improvements Phase I and II- $1,703,089
Phase I Renovation – $1,675,000
Architect: Black River Design
General Contractor: MLB
2005 Phase II -Renovation – renovate the other 1/2 of Prospect – $1,798,180
Architect: Black River Design
General Contractor: MLB