2006 Total project budget – $128,000,000
2003 Programming – $1,000,000
2004 Design: $2,000,000
Architect: Bohlin Cywinski Jackson
General Contractor: Barr & Barr
2005 Continued Design Work: $2,000,000
2006 Completion of Design and Construction: $123,000,000
2008 Off-Site Storage/Simonds Road Property Purchase and Development – $2,350,000
General Contractor: Barr & Barr